Aerial view of a highway interchange with overpasses, lanes under construction, and orange traffic cones.
Project

I81 Viaduct Project

  • Location: Syracuse, NY
  • Owner: New York State Department of Transportation - NYSDOT
  • Project Duration: 2023 - ongoing
  • Size: Approximately $771 Million

CONTRACT 1 (D900054),  CONTRACT 3 (D265218) & CONTRACT 5 (D265478)

CONTRACT 1 (D900054)

Project Details:

  • Contract Value: Approximately $296 Million
  • Owner: New York State Department of Transportation
  • Location: Syracuse, New York
  • Project Duration: 2023 – Ongoing

Project Description

This ongoing project is the first contract in the I-81 Viaduct Project.  Reconstructing the existing I-81/I-481 northern interchange into Business Loop 81 and I-81 and modifying portions of former I-481 from two to three lanes to the Kirkville Road interchange.  Work consists of 5 new bridges (all pile supported), 6 rehab bridges, 4 new culverts (3 of which are pile supported), 65 overhead sign structures, miles of Noise Wall, multiple Gravix walls, multiple embankments, sewer relocations, full depth reconstructions, drainage improvements, pavement resurfacing, and various landscape improvements.  This project has required sheet pile support of excavation at multiple locations and temporary bracing for the rehab structures.


CONTRACT 3 (D265218)

  • Contract Value: Approximately $224 Million
  • Owner: New York State Department of Transportation
  • Location: Syracuse, New York
  • Project Duration: 2024 – Ongoing

Project Description

The Interstate 81 Viaduct Project is one of the most significant transportation investments in New York State history—and a transformational moment for the City of Syracuse. With the award of the third major construction contract, work is now moving forward to replace the elevated I-81 highway in Downtown Syracuse with the new Community Grid, a multimodal-focused street network designed to reconnect neighborhoods, improve mobility, and support long-term economic growth across Central New York.

The third of nine construction contracts focuses on rebuilding key streets and interchanges on Syracuse’s northside and Inner Harbor. This phase will:

  • Consolidate multiple I-81 southbound on-and-off-ramps into one modern, safer connection to the future Business Loop (BL) 81.
  • Reconstruct North Clinton Street from Bear Street to Genant Drive, featuring new pavement, sidewalks, curbside parking, and a tree-lined shared-use path that enhances pedestrian and bicycle access.
  • Replace the Bear Street, Court Street, and Spencer Street bridges with wider, more accessible structures that include sidewalks and shared-use paths.
  • Improve safety for all travelers through curb bump-outs, enhanced pedestrian crossings, updated traffic signals, and decorative lighting.
  • Plant nearly 800 new trees and strengthen connections to existing regional assets like the Empire State Trail.
  • Upgrade the interchange of I-690 eastbound with Bear Street for a smoother, safer travel experience.

CONTRACT 5 (D265478)

  • Contract Value: Approximately $251 Million
  • Owner: New York State Department of Transportation
  • Location: Syracuse, New York
  • Project Duration: 2024 – Ongoing

Project Description

Contract Five focuses on the southern portion of the project area, where I-81 will be reconstructed and converted into the future Business Loop 81. This phase will:

  • Gradually bring the highway down to street level from Colvin Street to Burt Street, replacing the elevated structure.
  • Introduce traffic-calming features such as curved roadway alignments, narrower lanes, a landscaped median, street trees, and decorative lighting.
  • Create a smoother and safer approach toward Martin Luther King East.
  • Construct a new modern roundabout at Business Loop 81 and Van Buren Street—relocated from its original proposed position based on community feedback.
  • Beginning the Removal of the Viaduct

As work progresses, the viaduct will officially close to traffic south of Harrison Street, and approximately seven spans will be removed. Temporary modifications to Almond Street will maintain access to and from Business Loop 81 and ensure continued connectivity for travelers heading to the downtown core.

Project Gallery

Aerial view of a highway under construction with new lanes, an overpass, construction equipment, and orange traffic barrels.
High-angle view of a newly paved highway interchange with construction barrels and sparse traffic under a blue sky.
Aerial view of a newly paved highway with traffic, construction barrels, and an overpass under a cloudy sky.
Elevated view of a multi-lane highway interchange with construction work, orange traffic cones, and vehicles driving on open lanes.
Aerial view of a highway interchange with overpasses, lanes under construction, and orange traffic cones.
Aerial view of a newly paved highway interchange surrounded by trees and green spaces under an overcast sky.
Aerial view of a multilane highway running alongside an active construction site with machinery and earthworks.
Aerial view of a highway under construction with a newly installed bridge overpass framing multiple lanes of traffic, with a town and trees in the background.
Aerial view of a major highway construction project next to a multi-lane road and a large open field, with a city skyline in the distance.
Aerial view of a multilane highway passing under a bridge under construction, with surrounding urban buildings and parking lots.
Aerial view of a highway with construction work, running parallel to a railroad track and a dense expanse of autumn trees.

View More Projects