Cold Spring Construction partnered with Union Concrete to complete the excavation of approximately 550,000 Cubic Yards of dirt and rock for the “New Bills Stadium.” This involved drilling a line of 4”diameter holes 35’ deep around the perimeter of the stadium and then blasting a ring around the outside of the stadium. Then the Caterpillar D10 bulldozer came in and ripped the remaining rock from the bowl. All of the excavated Material was hauled to a site just west of Erie Community College via a purpose-built haul road along Southwestern Blvd. At the peak of the excavation there were 14 Caterpillar 740 Haul Trucks running 12 hrs. a day. Approximately 150,000 cubic yards was used to build the new parking lots to the west and south of the new stadium. Once the Bulldozer was close to the bottom elevation of the pit a Wirtgen Road Mill was brought in to cut the remaining 2ft of rock to a smooth surface to build on. This project was a great Collaboration of contractors working together to complete a common goal.